Molasses Pipeline Construction

Cowbit Treacle Mines PLC

Project Start: 15-Jul-2004      Project Finish: 09-Dec-2004

Task NameDurationStartFinishCostResources
Legal Work15-Jul-200416-Jul-20041000
Sign Contracts 1 day15-Jul-200416-Jul-20041000Lawyer
Physical Work16-Jul-200409-Dec-200422379
Pre Construction16-Jul-200423-Jul-20042879
Assemble Crews 5 days16-Jul-200423-Jul-20041799Foreman[0.60]
Assemble Equipment 3 days16-Jul-200421-Jul-20041080Foreman[0.60]
Construction23-Jul-200409-Dec-200419500
Excavate 6 days23-Jul-200402-Aug-20047200Foreman[0.50], Digging Machine, Truck[0.50], Labourer[3.00]
Lay Pipe 6 days26-Jul-200403-Aug-20046600Foreman[0.50], Labourer[2.00], Welder, Truck[0.50]
Backfill 6 days27-Jul-200404-Aug-20044200Labourer, Foreman
Landscape the ROW 5 days02-Dec-200409-Dec-20041500Gardener[2.00]


Guy Software Home Page
PlanBee Project Management product data