Task Name | Duration | Start | Latest Start | Finish | Latest Finish |
Contracts | | 04-Jun-2012 | 05-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
Supply Lot Sale Agreement | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
Supply Construction Agreement | 0 days | 04-Jun-2012 | 05-Jun-2012 | 04-Jun-2012 | 05-Jun-2012 |
Supply Contract Plans | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
Supply Contract Specifications | 0 days | 04-Jun-2012 | 05-Jun-2012 | 04-Jun-2012 | 05-Jun-2012 |
Supply Contract Site Plan | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
Secure Financing | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
Construction Loan Settlement | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
Document Review & Revision | | 04-Jun-2012 | 05-Jun-2012 | 09-Jul-2012 | 01-Aug-2012 |
Review & Finalize Plans | 15 days | 04-Jun-2012 | 11-Jun-2012 | 25-Jun-2012 | 02-Jul-2012 |
Review & Finalize Specifications | 20 days | 04-Jun-2012 | 05-Jun-2012 | 02-Jul-2012 | 03-Jul-2012 |
Review & Finalize Site Plan | 1 day | 25-Jun-2012 | 02-Jul-2012 | 26-Jun-2012 | 03-Jul-2012 |
Print Construction Drawings | 5 days | 02-Jul-2012 | 03-Jul-2012 | 09-Jul-2012 | 10-Jul-2012 |
Approve Revised Plans | 0 days | 09-Jul-2012 | 10-Jul-2012 | 09-Jul-2012 | 10-Jul-2012 |
Approve Revised Specifications | 0 days | 09-Jul-2012 | 11-Jul-2012 | 09-Jul-2012 | 11-Jul-2012 |
Approve Revised Site Plan | 0 days | 09-Jul-2012 | 01-Aug-2012 | 09-Jul-2012 | 01-Aug-2012 |
Bids & Contracts | | 09-Jul-2012 | 10-Jul-2012 | 10-Aug-2012 | 13-Aug-2012 |
Make Copies of Plans | 3 days | 09-Jul-2012 | 10-Jul-2012 | 12-Jul-2012 | 13-Jul-2012 |
Make Copies of Specifications | 2 days | 09-Jul-2012 | 11-Jul-2012 | 11-Jul-2012 | 13-Jul-2012 |
Distribute Plans & Specifications | 1 day | 12-Jul-2012 | 13-Jul-2012 | 13-Jul-2012 | 16-Jul-2012 |
Receive Bids | 10 days | 13-Jul-2012 | 16-Jul-2012 | 27-Jul-2012 | 30-Jul-2012 |
Review Bids | 5 days | 27-Jul-2012 | 30-Jul-2012 | 03-Aug-2012 | 06-Aug-2012 |
Execute Subcontractor Agreements | 5 days | 03-Aug-2012 | 06-Aug-2012 | 10-Aug-2012 | 13-Aug-2012 |
Grading & Building Permits | | 09-Jul-2012 | 01-Aug-2012 | 23-Aug-2012 | 24-Aug-2012 |
Schedule lot stake-out | 1 day | 09-Jul-2012 | 02-Aug-2012 | 10-Jul-2012 | 03-Aug-2012 |
Stake lot | 1 day | 13-Jul-2012 | 08-Aug-2012 | 16-Jul-2012 | 09-Aug-2012 |
File Grading Permit Application | 1 day | 09-Jul-2012 | 03-Aug-2012 | 10-Jul-2012 | 06-Aug-2012 |
File Building Permit Application | 3 days | 09-Jul-2012 | 01-Aug-2012 | 12-Jul-2012 | 06-Aug-2012 |
Post Lot Identification | 1 day | 16-Jul-2012 | 09-Aug-2012 | 17-Jul-2012 | 10-Aug-2012 |
Meet Sed. Control Insp. | 1 day | 17-Jul-2012 | 10-Aug-2012 | 18-Jul-2012 | 13-Aug-2012 |
Walk Lot w/ Owner | 1 day | 10-Aug-2012 | 13-Aug-2012 | 13-Aug-2012 | 14-Aug-2012 |
Install Construction Entrance | 1 day | 13-Aug-2012 | 15-Aug-2012 | 14-Aug-2012 | 16-Aug-2012 |
Install Sediment Controls | 2 days | 13-Aug-2012 | 14-Aug-2012 | 15-Aug-2012 | 16-Aug-2012 |
Sediment Control Insp. | 1 day | 15-Aug-2012 | 16-Aug-2012 | 16-Aug-2012 | 17-Aug-2012 |
Grading Permit Issued | 1 day | 16-Aug-2012 | 17-Aug-2012 | 17-Aug-2012 | 20-Aug-2012 |
Municipal Permit Process | 10 days | 12-Jul-2012 | 06-Aug-2012 | 26-Jul-2012 | 20-Aug-2012 |
Building Permit Approved | 1 day | 17-Aug-2012 | 20-Aug-2012 | 20-Aug-2012 | 21-Aug-2012 |
Pay Permit Fees and Excise Taxes | 1 day | 22-Aug-2012 | 23-Aug-2012 | 23-Aug-2012 | 24-Aug-2012 |
Building Permit Issued | 0 days | 23-Aug-2012 | 24-Aug-2012 | 23-Aug-2012 | 24-Aug-2012 |
Site Work | | 17-Aug-2012 | 21-Aug-2012 | 30-Aug-2012 | 31-Aug-2012 |
Clear Lot | 3 days | 17-Aug-2012 | 21-Aug-2012 | 22-Aug-2012 | 24-Aug-2012 |
Strip Topsoil & Stockpile | 1 day | 23-Aug-2012 | 24-Aug-2012 | 24-Aug-2012 | 27-Aug-2012 |
Stake Lot for Excavation | 1 day | 24-Aug-2012 | 27-Aug-2012 | 27-Aug-2012 | 28-Aug-2012 |
Rough grade lot | 1 day | 27-Aug-2012 | 28-Aug-2012 | 28-Aug-2012 | 29-Aug-2012 |
Excavate for foundation | 2 days | 28-Aug-2012 | 29-Aug-2012 | 30-Aug-2012 | 31-Aug-2012 |
Foundation | | 30-Aug-2012 | 31-Aug-2012 | 03-Oct-2012 | 16-Jan-2013 |
Layout footings | 1 day | 30-Aug-2012 | 31-Aug-2012 | 31-Aug-2012 | 03-Sep-2012 |
Dig Footings & Install Reinforcing | 1 day | 31-Aug-2012 | 03-Sep-2012 | 03-Sep-2012 | 04-Sep-2012 |
Footing Inspection | 0 days | 03-Sep-2012 | 04-Sep-2012 | 03-Sep-2012 | 04-Sep-2012 |
Pour footings | 1 day | 03-Sep-2012 | 04-Sep-2012 | 04-Sep-2012 | 05-Sep-2012 |
Pin Footings | 1 day | 04-Sep-2012 | 05-Sep-2012 | 05-Sep-2012 | 06-Sep-2012 |
Stock Block, Mortar, Sand | 1 day | 05-Sep-2012 | 06-Sep-2012 | 06-Sep-2012 | 07-Sep-2012 |
Build Block Foundation | 15 days | 06-Sep-2012 | 07-Sep-2012 | 27-Sep-2012 | 28-Sep-2012 |
Foundation Certification | 0 days | 27-Sep-2012 | 28-Sep-2012 | 27-Sep-2012 | 28-Sep-2012 |
Fill Block Cores w/ Concrete | 1 day | 27-Sep-2012 | 28-Sep-2012 | 28-Sep-2012 | 01-Oct-2012 |
Steel Delivery | 1 day | 28-Sep-2012 | 01-Oct-2012 | 01-Oct-2012 | 02-Oct-2012 |
Set Lintels, Bolts, Cap Block | 2 days | 01-Oct-2012 | 02-Oct-2012 | 03-Oct-2012 | 04-Oct-2012 |
Lumber Delivery | 1 day | 28-Sep-2012 | 03-Oct-2012 | 01-Oct-2012 | 04-Oct-2012 |
Waterproofing and Drain Tile | 1 day | 01-Oct-2012 | 15-Jan-2013 | 02-Oct-2012 | 16-Jan-2013 |
Rough Carpentry | | 04-Jun-2012 | 04-Oct-2012 | 19-Nov-2012 | 17-May-2013 |
Set Steel | 1 day | 03-Oct-2012 | 04-Oct-2012 | 04-Oct-2012 | 05-Oct-2012 |
1st Floor Deck Framing | 4 days | 04-Oct-2012 | 05-Oct-2012 | 10-Oct-2012 | 11-Oct-2012 |
1st Floor Wall Framing | 4 days | 10-Oct-2012 | 11-Oct-2012 | 16-Oct-2012 | 17-Oct-2012 |
2nd Floor Deck Framing | 2 days | 16-Oct-2012 | 17-Oct-2012 | 18-Oct-2012 | 19-Oct-2012 |
2nd Floor Wall Framing | 3 days | 18-Oct-2012 | 19-Oct-2012 | 23-Oct-2012 | 24-Oct-2012 |
Set Roof Trusses | 2 days | 23-Oct-2012 | 24-Oct-2012 | 25-Oct-2012 | 26-Oct-2012 |
Frame Roof | 7 days | 25-Oct-2012 | 26-Oct-2012 | 05-Nov-2012 | 06-Nov-2012 |
Install Roof Plywood | 5 days | 05-Nov-2012 | 06-Nov-2012 | 12-Nov-2012 | 13-Nov-2012 |
Install Windows & Doors | 2 days | 15-Nov-2012 | 16-Nov-2012 | 19-Nov-2012 | 20-Nov-2012 |
Frame Basement | 3 days | 13-Nov-2012 | 14-May-2013 | 16-Nov-2012 | 17-May-2013 |
REMOVE | 2 days | 04-Jun-2012 | 15-May-2013 | 06-Jun-2012 | 17-May-2013 |
Concrete Slabs | | 06-Nov-2012 | 16-Jan-2013 | 16-Nov-2012 | 03-May-2013 |
Basement Slab Preparation | 2 days | 06-Nov-2012 | 16-Jan-2013 | 08-Nov-2012 | 18-Jan-2013 |
Termite Treatment Basement Slab | 1 day | 08-Nov-2012 | 18-Jan-2013 | 09-Nov-2012 | 21-Jan-2013 |
Slab Inspection | 1 day | 09-Nov-2012 | 21-Jan-2013 | 12-Nov-2012 | 22-Jan-2013 |
Pour Basement Slab | 1 day | 12-Nov-2012 | 22-Jan-2013 | 13-Nov-2012 | 23-Jan-2013 |
Prep Garage Slab | 1 day | 13-Nov-2012 | 30-Apr-2013 | 14-Nov-2012 | 01-May-2013 |
Termite Treatment Garage Slab | 1 day | 14-Nov-2012 | 01-May-2013 | 15-Nov-2012 | 02-May-2013 |
Pour Garage Slab | 1 day | 15-Nov-2012 | 02-May-2013 | 16-Nov-2012 | 03-May-2013 |
H.V.A.C. | | 05-Nov-2012 | 29-Nov-2012 | 27-Nov-2012 | 25-Jan-2013 |
HVAC Layout & Measure | 1 day | 05-Nov-2012 | 29-Nov-2012 | 06-Nov-2012 | 30-Nov-2012 |
HVAC Rough-in | 5 days | 15-Nov-2012 | 30-Nov-2012 | 22-Nov-2012 | 07-Dec-2012 |
HVAC Set Indoor Units | 2 days | 22-Nov-2012 | 23-Jan-2013 | 26-Nov-2012 | 25-Jan-2013 |
HVAC Temporary Heat | 2 days | 23-Nov-2012 | 21-Dec-2012 | 27-Nov-2012 | 25-Dec-2012 |
Plumbing Rough-in | | 10-Oct-2012 | 05-Dec-2012 | 30-Nov-2012 | 17-Dec-2012 |
Plumbing Sub-slab | 2 days | 10-Oct-2012 | 05-Dec-2012 | 12-Oct-2012 | 07-Dec-2012 |
Plumbing Layout | 1 day | 22-Nov-2012 | 07-Dec-2012 | 23-Nov-2012 | 10-Dec-2012 |
Plumbing rough-in | 5 days | 23-Nov-2012 | 10-Dec-2012 | 30-Nov-2012 | 17-Dec-2012 |
Municipal Plumbing Sub-slab Inspection | 0 days | 12-Oct-2012 | 10-Dec-2012 | 12-Oct-2012 | 10-Dec-2012 |
Municipal Plumbing Rough-in Inspection | 0 days | 30-Nov-2012 | 17-Dec-2012 | 30-Nov-2012 | 17-Dec-2012 |
Electric Rough-in | | 19-Nov-2012 | 20-Nov-2012 | 14-Dec-2012 | 17-Dec-2012 |
Set Electric Boxes | 2 days | 19-Nov-2012 | 20-Nov-2012 | 21-Nov-2012 | 22-Nov-2012 |
Install Electric Service Panel | 2 days | 21-Nov-2012 | 22-Nov-2012 | 23-Nov-2012 | 26-Nov-2012 |
Electrical Walk-through | 1 day | 23-Nov-2012 | 26-Nov-2012 | 26-Nov-2012 | 27-Nov-2012 |
Electrical Rough-wire | 14 days | 26-Nov-2012 | 27-Nov-2012 | 14-Dec-2012 | 17-Dec-2012 |
Specialty Rough-ins | | 14-Dec-2012 | 17-Dec-2012 | 28-Dec-2012 | 08-Mar-2013 |
Central Vacuum Rough-in | 5 days | 14-Dec-2012 | 01-Mar-2013 | 21-Dec-2012 | 08-Mar-2013 |
Alarm System Rough-in | 5 days | 14-Dec-2012 | 01-Mar-2013 | 21-Dec-2012 | 08-Mar-2013 |
Telephone System Rough-in | 5 days | 14-Dec-2012 | 22-Feb-2013 | 21-Dec-2012 | 01-Mar-2013 |
Television System Rough-in | 5 days | 21-Dec-2012 | 01-Mar-2013 | 28-Dec-2012 | 08-Mar-2013 |
Audio Visual Rough-in | 5 days | 14-Dec-2012 | 01-Mar-2013 | 21-Dec-2012 | 08-Mar-2013 |
Municipal Electrical inspection | 0 days | 14-Dec-2012 | 17-Dec-2012 | 14-Dec-2012 | 17-Dec-2012 |
Municipal Framing Inspection | 0 days | 17-Dec-2012 | 18-Dec-2012 | 17-Dec-2012 | 18-Dec-2012 |
Roofing | | 12-Nov-2012 | 13-Nov-2012 | 14-Feb-2013 | 03-May-2013 |
Roofing Paper Installed | 3 days | 12-Nov-2012 | 13-Nov-2012 | 15-Nov-2012 | 16-Nov-2012 |
Stock Roof Shingles | 1 day | 15-Nov-2012 | 23-Apr-2013 | 16-Nov-2012 | 24-Apr-2013 |
Install Roof Shingles | 7 days | 05-Feb-2013 | 24-Apr-2013 | 14-Feb-2013 | 03-May-2013 |
Exterior Finishes | | 19-Nov-2012 | 01-Jan-2013 | 05-Feb-2013 | 20-Mar-2013 |
Siding | 3 days | 19-Nov-2012 | 01-Jan-2013 | 22-Nov-2012 | 04-Jan-2013 |
Exterior Trim | 7 days | 22-Nov-2012 | 04-Jan-2013 | 03-Dec-2012 | 15-Jan-2013 |
Brick Arch Forms | 1 day | 03-Dec-2012 | 15-Jan-2013 | 04-Dec-2012 | 16-Jan-2013 |
Brick Veneer | 45 days | 04-Dec-2012 | 16-Jan-2013 | 05-Feb-2013 | 20-Mar-2013 |
Insulation | | 17-Dec-2012 | 18-Dec-2012 | 24-Dec-2012 | 25-Dec-2012 |
Caulk & Air Seal | 1 day | 17-Dec-2012 | 18-Dec-2012 | 18-Dec-2012 | 19-Dec-2012 |
Draft & Fire Stop | 1 day | 18-Dec-2012 | 19-Dec-2012 | 19-Dec-2012 | 20-Dec-2012 |
Batt Insulation | 3 days | 19-Dec-2012 | 20-Dec-2012 | 24-Dec-2012 | 25-Dec-2012 |
Municipal Insulation Inspection | 0 days | 24-Dec-2012 | 25-Dec-2012 | 24-Dec-2012 | 25-Dec-2012 |
Drywall | | 24-Dec-2012 | 25-Dec-2012 | 29-Jan-2013 | 27-Mar-2013 |
Stock Drywall | 1 day | 24-Dec-2012 | 25-Dec-2012 | 25-Dec-2012 | 26-Dec-2012 |
Hang Drywall | 5 days | 25-Dec-2012 | 26-Dec-2012 | 01-Jan-2013 | 02-Jan-2013 |
Remove Scrap Drywall | 1 day | 01-Jan-2013 | 02-Jan-2013 | 02-Jan-2013 | 03-Jan-2013 |
Tape and Finish Drywall | 15 days | 02-Jan-2013 | 03-Jan-2013 | 23-Jan-2013 | 24-Jan-2013 |
Sand Drywall | 1 day | 23-Jan-2013 | 24-Jan-2013 | 24-Jan-2013 | 25-Jan-2013 |
Drywall Point-up | 3 days | 24-Jan-2013 | 22-Mar-2013 | 29-Jan-2013 | 27-Mar-2013 |
Floor Finishes | | 30-Jan-2013 | 05-Apr-2013 | 02-May-2013 | 17-May-2013 |
Ceramic Tile | 15 days | 30-Jan-2013 | 05-Apr-2013 | 20-Feb-2013 | 26-Apr-2013 |
Install Hardwood Floor | 4 days | 15-Apr-2013 | 16-Apr-2013 | 19-Apr-2013 | 22-Apr-2013 |
Sand, Stain, Seal Hardwood | 5 days | 19-Apr-2013 | 22-Apr-2013 | 26-Apr-2013 | 29-Apr-2013 |
Install Carpet | 4 days | 26-Apr-2013 | 29-Apr-2013 | 02-May-2013 | 03-May-2013 |
Final Coat Hardwood | 2 days | 26-Apr-2013 | 15-May-2013 | 30-Apr-2013 | 17-May-2013 |
Paint | | 24-Jan-2013 | 25-Jan-2013 | 17-Apr-2013 | 03-May-2013 |
Prep Drywall for Prime Coat | 2 days | 24-Jan-2013 | 25-Jan-2013 | 28-Jan-2013 | 29-Jan-2013 |
Prime Paint Drywall | 2 days | 28-Jan-2013 | 29-Jan-2013 | 30-Jan-2013 | 31-Jan-2013 |
Prep Trim for Prime Coat | 2 days | 07-Feb-2013 | 05-Mar-2013 | 11-Feb-2013 | 07-Mar-2013 |
Prime Trim | 2 days | 11-Feb-2013 | 07-Mar-2013 | 13-Feb-2013 | 11-Mar-2013 |
Finish Coat Trim | 10 days | 12-Mar-2013 | 13-Mar-2013 | 26-Mar-2013 | 27-Mar-2013 |
Finish Coat Drywall | 14 days | 26-Mar-2013 | 27-Mar-2013 | 15-Apr-2013 | 16-Apr-2013 |
Caulk Exterior Windows & Doors | 1 day | 15-Apr-2013 | 01-May-2013 | 16-Apr-2013 | 02-May-2013 |
Finish Coat Exterior Trim & Siding | 1 day | 16-Apr-2013 | 02-May-2013 | 17-Apr-2013 | 03-May-2013 |
Interior Trim | | 30-Jan-2013 | 31-Jan-2013 | 12-Mar-2013 | 13-Mar-2013 |
Interior Trim Delivery | 1 day | 30-Jan-2013 | 31-Jan-2013 | 31-Jan-2013 | 01-Feb-2013 |
Install Interior Doors | 5 days | 31-Jan-2013 | 01-Feb-2013 | 07-Feb-2013 | 08-Feb-2013 |
Install Interior Trim | 15 days | 07-Feb-2013 | 08-Feb-2013 | 28-Feb-2013 | 01-Mar-2013 |
Install Cabinetry | 5 days | 28-Feb-2013 | 01-Mar-2013 | 07-Mar-2013 | 08-Mar-2013 |
Install Appliances | 1 day | 07-Mar-2013 | 08-Mar-2013 | 08-Mar-2013 | 11-Mar-2013 |
1st Punch-out Interior Trim | 2 days | 08-Mar-2013 | 11-Mar-2013 | 12-Mar-2013 | 13-Mar-2013 |
H.V.A.C. Trim | | 24-Jan-2013 | 12-Mar-2013 | 07-Feb-2013 | 30-Apr-2013 |
Install Grills & Registers for Paint | 1 day | 24-Jan-2013 | 12-Mar-2013 | 25-Jan-2013 | 13-Mar-2013 |
Set Outdoor Units | 1 day | 06-Feb-2013 | 29-Apr-2013 | 07-Feb-2013 | 30-Apr-2013 |
Plumbing Trim | | 19-Apr-2013 | 26-Apr-2013 | 26-Apr-2013 | 03-May-2013 |
Set Fixtures | 4 days | 19-Apr-2013 | 26-Apr-2013 | 25-Apr-2013 | 02-May-2013 |
Connect Appliances | 1 day | 25-Apr-2013 | 02-May-2013 | 26-Apr-2013 | 03-May-2013 |
Municipal Final Plumbing Inspection | 0 days | 26-Apr-2013 | 03-May-2013 | 26-Apr-2013 | 03-May-2013 |
Exterior Landscaping | | 05-Feb-2013 | 20-Mar-2013 | 21-Mar-2013 | 03-May-2013 |
Rough Final Grade | 1 day | 05-Feb-2013 | 20-Mar-2013 | 06-Feb-2013 | 21-Mar-2013 |
Patios | 7 days | 06-Feb-2013 | 21-Mar-2013 | 15-Feb-2013 | 01-Apr-2013 |
Porches | 5 days | 15-Feb-2013 | 01-Apr-2013 | 22-Feb-2013 | 08-Apr-2013 |
Sidewalks | 7 days | 22-Feb-2013 | 08-Apr-2013 | 05-Mar-2013 | 17-Apr-2013 |
Decks | 7 days | 05-Mar-2013 | 17-Apr-2013 | 14-Mar-2013 | 26-Apr-2013 |
Driveways | 2 days | 14-Mar-2013 | 26-Apr-2013 | 18-Mar-2013 | 30-Apr-2013 |
Final Grade and Seed | 3 days | 18-Mar-2013 | 30-Apr-2013 | 21-Mar-2013 | 03-May-2013 |
Electrical Final Trim | | 30-Jan-2013 | 29-Apr-2013 | 11-Mar-2013 | 03-May-2013 |
Switch & Plug | 2 days | 30-Jan-2013 | 29-Apr-2013 | 01-Feb-2013 | 01-May-2013 |
Install Fixtures | 1 day | 01-Feb-2013 | 01-May-2013 | 04-Feb-2013 | 02-May-2013 |
Connect Appliances | 1 day | 08-Mar-2013 | 02-May-2013 | 11-Mar-2013 | 03-May-2013 |
Hardware | | 15-Apr-2013 | 17-Apr-2013 | 06-May-2013 | 06-May-2013 |
Door Hardware | 2 days | 15-Apr-2013 | 01-May-2013 | 17-Apr-2013 | 03-May-2013 |
Bath Hardware | 2 days | 15-Apr-2013 | 17-Apr-2013 | 17-Apr-2013 | 19-Apr-2013 |
Mirrors | 5 days | 17-Apr-2013 | 26-Apr-2013 | 24-Apr-2013 | 03-May-2013 |
Shower Doors | 10 days | 17-Apr-2013 | 19-Apr-2013 | 01-May-2013 | 03-May-2013 |
Final Building Inspection | 0 days | 02-May-2013 | 03-May-2013 | 02-May-2013 | 03-May-2013 |
Use & Occupancy Certificate | 0 days | 06-May-2013 | 06-May-2013 | 06-May-2013 | 06-May-2013 |
First Walk-thru | 0 days | 06-May-2013 | 06-May-2013 | 06-May-2013 | 06-May-2013 |
Final Punch-out | | 06-May-2013 | 06-May-2013 | 17-May-2013 | 17-May-2013 |
Punch Out Walk-thru List | 4 days | 06-May-2013 | 06-May-2013 | 10-May-2013 | 10-May-2013 |
Trim and Adjust Doors | 2 days | 10-May-2013 | 10-May-2013 | 14-May-2013 | 14-May-2013 |
Paint Touch-up | 3 days | 14-May-2013 | 14-May-2013 | 17-May-2013 | 17-May-2013 |
Cleaning | | 15-Apr-2013 | 06-May-2013 | 17-May-2013 | 17-May-2013 |
Windows | 3 days | 15-Apr-2013 | 06-May-2013 | 18-Apr-2013 | 09-May-2013 |
Rough Clean | 3 days | 18-Apr-2013 | 09-May-2013 | 23-Apr-2013 | 14-May-2013 |
Final Clean | 2 days | 14-May-2013 | 14-May-2013 | 16-May-2013 | 16-May-2013 |
Final Walk-through | 0 days | 16-May-2013 | 16-May-2013 | 16-May-2013 | 16-May-2013 |
Move-in | 0 days | 17-May-2013 | 17-May-2013 | 17-May-2013 | 17-May-2013 |