Fred's Construction

Project Start: 04-Jun-2012      Project Finish: 17-May-2013

Task NameDurationStartLatest StartFinishLatest Finish
Contracts04-Jun-201205-Jun-201204-Jun-201211-Jun-2012
Supply Lot Sale Agreement 0 days04-Jun-201211-Jun-201204-Jun-201211-Jun-2012
Supply Construction Agreement 0 days04-Jun-201205-Jun-201204-Jun-201205-Jun-2012
Supply Contract Plans 0 days04-Jun-201211-Jun-201204-Jun-201211-Jun-2012
Supply Contract Specifications 0 days04-Jun-201205-Jun-201204-Jun-201205-Jun-2012
Supply Contract Site Plan 0 days04-Jun-201211-Jun-201204-Jun-201211-Jun-2012
Secure Financing 0 days04-Jun-201211-Jun-201204-Jun-201211-Jun-2012
Construction Loan Settlement 0 days04-Jun-201211-Jun-201204-Jun-201211-Jun-2012
Document Review & Revision04-Jun-201205-Jun-201209-Jul-201201-Aug-2012
Review & Finalize Plans 15 days04-Jun-201211-Jun-201225-Jun-201202-Jul-2012
Review & Finalize Specifications 20 days04-Jun-201205-Jun-201202-Jul-201203-Jul-2012
Review & Finalize Site Plan 1 day25-Jun-201202-Jul-201226-Jun-201203-Jul-2012
Print Construction Drawings 5 days02-Jul-201203-Jul-201209-Jul-201210-Jul-2012
Approve Revised Plans 0 days09-Jul-201210-Jul-201209-Jul-201210-Jul-2012
Approve Revised Specifications 0 days09-Jul-201211-Jul-201209-Jul-201211-Jul-2012
Approve Revised Site Plan 0 days09-Jul-201201-Aug-201209-Jul-201201-Aug-2012
Bids & Contracts09-Jul-201210-Jul-201210-Aug-201213-Aug-2012
Make Copies of Plans 3 days09-Jul-201210-Jul-201212-Jul-201213-Jul-2012
Make Copies of Specifications 2 days09-Jul-201211-Jul-201211-Jul-201213-Jul-2012
Distribute Plans & Specifications 1 day12-Jul-201213-Jul-201213-Jul-201216-Jul-2012
Receive Bids 10 days13-Jul-201216-Jul-201227-Jul-201230-Jul-2012
Review Bids 5 days27-Jul-201230-Jul-201203-Aug-201206-Aug-2012
Execute Subcontractor Agreements 5 days03-Aug-201206-Aug-201210-Aug-201213-Aug-2012
Grading & Building Permits09-Jul-201201-Aug-201223-Aug-201224-Aug-2012
Schedule lot stake-out 1 day09-Jul-201202-Aug-201210-Jul-201203-Aug-2012
Stake lot 1 day13-Jul-201208-Aug-201216-Jul-201209-Aug-2012
File Grading Permit Application 1 day09-Jul-201203-Aug-201210-Jul-201206-Aug-2012
File Building Permit Application 3 days09-Jul-201201-Aug-201212-Jul-201206-Aug-2012
Post Lot Identification 1 day16-Jul-201209-Aug-201217-Jul-201210-Aug-2012
Meet Sed. Control Insp. 1 day17-Jul-201210-Aug-201218-Jul-201213-Aug-2012
Walk Lot w/ Owner 1 day10-Aug-201213-Aug-201213-Aug-201214-Aug-2012
Install Construction Entrance 1 day13-Aug-201215-Aug-201214-Aug-201216-Aug-2012
Install Sediment Controls 2 days13-Aug-201214-Aug-201215-Aug-201216-Aug-2012
Sediment Control Insp. 1 day15-Aug-201216-Aug-201216-Aug-201217-Aug-2012
Grading Permit Issued 1 day16-Aug-201217-Aug-201217-Aug-201220-Aug-2012
Municipal Permit Process 10 days12-Jul-201206-Aug-201226-Jul-201220-Aug-2012
Building Permit Approved 1 day17-Aug-201220-Aug-201220-Aug-201221-Aug-2012
Pay Permit Fees and Excise Taxes 1 day22-Aug-201223-Aug-201223-Aug-201224-Aug-2012
Building Permit Issued 0 days23-Aug-201224-Aug-201223-Aug-201224-Aug-2012
Site Work17-Aug-201221-Aug-201230-Aug-201231-Aug-2012
Clear Lot 3 days17-Aug-201221-Aug-201222-Aug-201224-Aug-2012
Strip Topsoil & Stockpile 1 day23-Aug-201224-Aug-201224-Aug-201227-Aug-2012
Stake Lot for Excavation 1 day24-Aug-201227-Aug-201227-Aug-201228-Aug-2012
Rough grade lot 1 day27-Aug-201228-Aug-201228-Aug-201229-Aug-2012
Excavate for foundation 2 days28-Aug-201229-Aug-201230-Aug-201231-Aug-2012
Foundation30-Aug-201231-Aug-201203-Oct-201216-Jan-2013
Layout footings 1 day30-Aug-201231-Aug-201231-Aug-201203-Sep-2012
Dig Footings & Install Reinforcing 1 day31-Aug-201203-Sep-201203-Sep-201204-Sep-2012
Footing Inspection 0 days03-Sep-201204-Sep-201203-Sep-201204-Sep-2012
Pour footings 1 day03-Sep-201204-Sep-201204-Sep-201205-Sep-2012
Pin Footings 1 day04-Sep-201205-Sep-201205-Sep-201206-Sep-2012
Stock Block, Mortar, Sand 1 day05-Sep-201206-Sep-201206-Sep-201207-Sep-2012
Build Block Foundation 15 days06-Sep-201207-Sep-201227-Sep-201228-Sep-2012
Foundation Certification 0 days27-Sep-201228-Sep-201227-Sep-201228-Sep-2012
Fill Block Cores w/ Concrete 1 day27-Sep-201228-Sep-201228-Sep-201201-Oct-2012
Steel Delivery 1 day28-Sep-201201-Oct-201201-Oct-201202-Oct-2012
Set Lintels, Bolts, Cap Block 2 days01-Oct-201202-Oct-201203-Oct-201204-Oct-2012
Lumber Delivery 1 day28-Sep-201203-Oct-201201-Oct-201204-Oct-2012
Waterproofing and Drain Tile 1 day01-Oct-201215-Jan-201302-Oct-201216-Jan-2013
Rough Carpentry04-Jun-201204-Oct-201219-Nov-201217-May-2013
Set Steel 1 day03-Oct-201204-Oct-201204-Oct-201205-Oct-2012
1st Floor Deck Framing 4 days04-Oct-201205-Oct-201210-Oct-201211-Oct-2012
1st Floor Wall Framing 4 days10-Oct-201211-Oct-201216-Oct-201217-Oct-2012
2nd Floor Deck Framing 2 days16-Oct-201217-Oct-201218-Oct-201219-Oct-2012
2nd Floor Wall Framing 3 days18-Oct-201219-Oct-201223-Oct-201224-Oct-2012
Set Roof Trusses 2 days23-Oct-201224-Oct-201225-Oct-201226-Oct-2012
Frame Roof 7 days25-Oct-201226-Oct-201205-Nov-201206-Nov-2012
Install Roof Plywood 5 days05-Nov-201206-Nov-201212-Nov-201213-Nov-2012
Install Windows & Doors 2 days15-Nov-201216-Nov-201219-Nov-201220-Nov-2012
Frame Basement 3 days13-Nov-201214-May-201316-Nov-201217-May-2013
REMOVE 2 days04-Jun-201215-May-201306-Jun-201217-May-2013
Concrete Slabs06-Nov-201216-Jan-201316-Nov-201203-May-2013
Basement Slab Preparation 2 days06-Nov-201216-Jan-201308-Nov-201218-Jan-2013
Termite Treatment Basement Slab 1 day08-Nov-201218-Jan-201309-Nov-201221-Jan-2013
Slab Inspection 1 day09-Nov-201221-Jan-201312-Nov-201222-Jan-2013
Pour Basement Slab 1 day12-Nov-201222-Jan-201313-Nov-201223-Jan-2013
Prep Garage Slab 1 day13-Nov-201230-Apr-201314-Nov-201201-May-2013
Termite Treatment Garage Slab 1 day14-Nov-201201-May-201315-Nov-201202-May-2013
Pour Garage Slab 1 day15-Nov-201202-May-201316-Nov-201203-May-2013
H.V.A.C.05-Nov-201229-Nov-201227-Nov-201225-Jan-2013
HVAC Layout & Measure 1 day05-Nov-201229-Nov-201206-Nov-201230-Nov-2012
HVAC Rough-in 5 days15-Nov-201230-Nov-201222-Nov-201207-Dec-2012
HVAC Set Indoor Units 2 days22-Nov-201223-Jan-201326-Nov-201225-Jan-2013
HVAC Temporary Heat 2 days23-Nov-201221-Dec-201227-Nov-201225-Dec-2012
Plumbing Rough-in10-Oct-201205-Dec-201230-Nov-201217-Dec-2012
Plumbing Sub-slab 2 days10-Oct-201205-Dec-201212-Oct-201207-Dec-2012
Plumbing Layout 1 day22-Nov-201207-Dec-201223-Nov-201210-Dec-2012
Plumbing rough-in 5 days23-Nov-201210-Dec-201230-Nov-201217-Dec-2012
Municipal Plumbing Sub-slab Inspection 0 days12-Oct-201210-Dec-201212-Oct-201210-Dec-2012
Municipal Plumbing Rough-in Inspection 0 days30-Nov-201217-Dec-201230-Nov-201217-Dec-2012
Electric Rough-in19-Nov-201220-Nov-201214-Dec-201217-Dec-2012
Set Electric Boxes 2 days19-Nov-201220-Nov-201221-Nov-201222-Nov-2012
Install Electric Service Panel 2 days21-Nov-201222-Nov-201223-Nov-201226-Nov-2012
Electrical Walk-through 1 day23-Nov-201226-Nov-201226-Nov-201227-Nov-2012
Electrical Rough-wire 14 days26-Nov-201227-Nov-201214-Dec-201217-Dec-2012
Specialty Rough-ins14-Dec-201217-Dec-201228-Dec-201208-Mar-2013
Central Vacuum Rough-in 5 days14-Dec-201201-Mar-201321-Dec-201208-Mar-2013
Alarm System Rough-in 5 days14-Dec-201201-Mar-201321-Dec-201208-Mar-2013
Telephone System Rough-in 5 days14-Dec-201222-Feb-201321-Dec-201201-Mar-2013
Television System Rough-in 5 days21-Dec-201201-Mar-201328-Dec-201208-Mar-2013
Audio Visual Rough-in 5 days14-Dec-201201-Mar-201321-Dec-201208-Mar-2013
Municipal Electrical inspection 0 days14-Dec-201217-Dec-201214-Dec-201217-Dec-2012
Municipal Framing Inspection 0 days17-Dec-201218-Dec-201217-Dec-201218-Dec-2012
Roofing12-Nov-201213-Nov-201214-Feb-201303-May-2013
Roofing Paper Installed 3 days12-Nov-201213-Nov-201215-Nov-201216-Nov-2012
Stock Roof Shingles 1 day15-Nov-201223-Apr-201316-Nov-201224-Apr-2013
Install Roof Shingles 7 days05-Feb-201324-Apr-201314-Feb-201303-May-2013
Exterior Finishes19-Nov-201201-Jan-201305-Feb-201320-Mar-2013
Siding 3 days19-Nov-201201-Jan-201322-Nov-201204-Jan-2013
Exterior Trim 7 days22-Nov-201204-Jan-201303-Dec-201215-Jan-2013
Brick Arch Forms 1 day03-Dec-201215-Jan-201304-Dec-201216-Jan-2013
Brick Veneer 45 days04-Dec-201216-Jan-201305-Feb-201320-Mar-2013
Insulation17-Dec-201218-Dec-201224-Dec-201225-Dec-2012
Caulk & Air Seal 1 day17-Dec-201218-Dec-201218-Dec-201219-Dec-2012
Draft & Fire Stop 1 day18-Dec-201219-Dec-201219-Dec-201220-Dec-2012
Batt Insulation 3 days19-Dec-201220-Dec-201224-Dec-201225-Dec-2012
Municipal Insulation Inspection 0 days24-Dec-201225-Dec-201224-Dec-201225-Dec-2012
Drywall24-Dec-201225-Dec-201229-Jan-201327-Mar-2013
Stock Drywall 1 day24-Dec-201225-Dec-201225-Dec-201226-Dec-2012
Hang Drywall 5 days25-Dec-201226-Dec-201201-Jan-201302-Jan-2013
Remove Scrap Drywall 1 day01-Jan-201302-Jan-201302-Jan-201303-Jan-2013
Tape and Finish Drywall 15 days02-Jan-201303-Jan-201323-Jan-201324-Jan-2013
Sand Drywall 1 day23-Jan-201324-Jan-201324-Jan-201325-Jan-2013
Drywall Point-up 3 days24-Jan-201322-Mar-201329-Jan-201327-Mar-2013
Floor Finishes30-Jan-201305-Apr-201302-May-201317-May-2013
Ceramic Tile 15 days30-Jan-201305-Apr-201320-Feb-201326-Apr-2013
Install Hardwood Floor 4 days15-Apr-201316-Apr-201319-Apr-201322-Apr-2013
Sand, Stain, Seal Hardwood 5 days19-Apr-201322-Apr-201326-Apr-201329-Apr-2013
Install Carpet 4 days26-Apr-201329-Apr-201302-May-201303-May-2013
Final Coat Hardwood 2 days26-Apr-201315-May-201330-Apr-201317-May-2013
Paint24-Jan-201325-Jan-201317-Apr-201303-May-2013
Prep Drywall for Prime Coat 2 days24-Jan-201325-Jan-201328-Jan-201329-Jan-2013
Prime Paint Drywall 2 days28-Jan-201329-Jan-201330-Jan-201331-Jan-2013
Prep Trim for Prime Coat 2 days07-Feb-201305-Mar-201311-Feb-201307-Mar-2013
Prime Trim 2 days11-Feb-201307-Mar-201313-Feb-201311-Mar-2013
Finish Coat Trim 10 days12-Mar-201313-Mar-201326-Mar-201327-Mar-2013
Finish Coat Drywall 14 days26-Mar-201327-Mar-201315-Apr-201316-Apr-2013
Caulk Exterior Windows & Doors 1 day15-Apr-201301-May-201316-Apr-201302-May-2013
Finish Coat Exterior Trim & Siding 1 day16-Apr-201302-May-201317-Apr-201303-May-2013
Interior Trim30-Jan-201331-Jan-201312-Mar-201313-Mar-2013
Interior Trim Delivery 1 day30-Jan-201331-Jan-201331-Jan-201301-Feb-2013
Install Interior Doors 5 days31-Jan-201301-Feb-201307-Feb-201308-Feb-2013
Install Interior Trim 15 days07-Feb-201308-Feb-201328-Feb-201301-Mar-2013
Install Cabinetry 5 days28-Feb-201301-Mar-201307-Mar-201308-Mar-2013
Install Appliances 1 day07-Mar-201308-Mar-201308-Mar-201311-Mar-2013
1st Punch-out Interior Trim 2 days08-Mar-201311-Mar-201312-Mar-201313-Mar-2013
H.V.A.C. Trim24-Jan-201312-Mar-201307-Feb-201330-Apr-2013
Install Grills & Registers for Paint 1 day24-Jan-201312-Mar-201325-Jan-201313-Mar-2013
Set Outdoor Units 1 day06-Feb-201329-Apr-201307-Feb-201330-Apr-2013
Plumbing Trim19-Apr-201326-Apr-201326-Apr-201303-May-2013
Set Fixtures 4 days19-Apr-201326-Apr-201325-Apr-201302-May-2013
Connect Appliances 1 day25-Apr-201302-May-201326-Apr-201303-May-2013
Municipal Final Plumbing Inspection 0 days26-Apr-201303-May-201326-Apr-201303-May-2013
Exterior Landscaping05-Feb-201320-Mar-201321-Mar-201303-May-2013
Rough Final Grade 1 day05-Feb-201320-Mar-201306-Feb-201321-Mar-2013
Patios 7 days06-Feb-201321-Mar-201315-Feb-201301-Apr-2013
Porches 5 days15-Feb-201301-Apr-201322-Feb-201308-Apr-2013
Sidewalks 7 days22-Feb-201308-Apr-201305-Mar-201317-Apr-2013
Decks 7 days05-Mar-201317-Apr-201314-Mar-201326-Apr-2013
Driveways 2 days14-Mar-201326-Apr-201318-Mar-201330-Apr-2013
Final Grade and Seed 3 days18-Mar-201330-Apr-201321-Mar-201303-May-2013
Electrical Final Trim30-Jan-201329-Apr-201311-Mar-201303-May-2013
Switch & Plug 2 days30-Jan-201329-Apr-201301-Feb-201301-May-2013
Install Fixtures 1 day01-Feb-201301-May-201304-Feb-201302-May-2013
Connect Appliances 1 day08-Mar-201302-May-201311-Mar-201303-May-2013
Hardware15-Apr-201317-Apr-201306-May-201306-May-2013
Door Hardware 2 days15-Apr-201301-May-201317-Apr-201303-May-2013
Bath Hardware 2 days15-Apr-201317-Apr-201317-Apr-201319-Apr-2013
Mirrors 5 days17-Apr-201326-Apr-201324-Apr-201303-May-2013
Shower Doors 10 days17-Apr-201319-Apr-201301-May-201303-May-2013
Final Building Inspection 0 days02-May-201303-May-201302-May-201303-May-2013
Use & Occupancy Certificate 0 days06-May-201306-May-201306-May-201306-May-2013
First Walk-thru 0 days06-May-201306-May-201306-May-201306-May-2013
Final Punch-out06-May-201306-May-201317-May-201317-May-2013
Punch Out Walk-thru List 4 days06-May-201306-May-201310-May-201310-May-2013
Trim and Adjust Doors 2 days10-May-201310-May-201314-May-201314-May-2013
Paint Touch-up 3 days14-May-201314-May-201317-May-201317-May-2013
Cleaning15-Apr-201306-May-201317-May-201317-May-2013
Windows 3 days15-Apr-201306-May-201318-Apr-201309-May-2013
Rough Clean 3 days18-Apr-201309-May-201323-Apr-201314-May-2013
Final Clean 2 days14-May-201314-May-201316-May-201316-May-2013
Final Walk-through 0 days16-May-201316-May-201316-May-201316-May-2013
Move-in 0 days17-May-201317-May-201317-May-201317-May-2013